Construction
Preparation and pouring of the concrete ceiling
Since our last report on the pouring of 38 columns earlier in July, we are thrilled to share yet another update on the progress of the Nile Institute Rwanda construction works.
Since our last report on the pouring of 38 columns earlier in July, we are thrilled to share yet another update on the progress of the Nile Institute Rwanda construction works.
The concrete floor slab was poured at the end of June. The drying out of the 15 cm thick slab takes 28 days. It is watered daily to prevent too rapid drying and reduced quality. Time to start the next phase: preparation for pouring the columns.
After a lot of preparation works, the 28th & 29th of June mark an important milestone for the Nile Institute Rwanda. With the help of more than 100 people from the village, the concrete floor plate was poured, finishing the foundation works on schedule!
Learn and see more of the next phase of the Nile Institute construction; the Foundation works. 36 foundation wells are constructed on the site.